Auxiliary structure to support the assembly of the railway bridge over the Mearim River, Maranhão

Vitória do Mearim, MA

BACK TO ALL PROJECTS

Location

Vitória do Mearim, MA

Phase

Construído

Partnerships

Martifer Construções

Photography

-

SP.PROJECT was responsible for the development of an auxiliary structure, designed to allow the bridge to be assembled by an incremental launch process. The anterior "nose" has a development of 42.5m and the posterior structure has a development of 7.0m. These two structures allowed the launch of a 72.3m long bridge module.